Block -A- 5th Roof Slab Shuttering Work in Progress Block -B- 2nd Roof Steel Reinforcement Work in Progress Block -C- Bar Bending & Raft Slab Concreting Work in Progress 20th December 2011 Updation Schedule
Block -A- 3rd Floor Roof Slab and Bar Bending Work in Progress Block -B- 1st Floor Column Concreting Work in Progress Block -C- PCC Column Marking Work in Progress 5th December 2011 Updation Schedule
Block - A - 2nd Floor Roof Slab and Bar Bending Work in Progress Block - B - Column Marking and Bar Bending Work in Progress Block - C - Earth Excavation Work in Progress |